_
Numerous work experiences of the company
Description | Employer | Date of Contract | Cost of Project, (Million Rials) | Infrastructure (m2) | 1st stage | 2nd stage | Supervision | Project Status | |
---|---|---|---|---|---|---|---|---|---|
1 | Faculty of architecture, mechanics, and construction | Iran University of Science & Technology | 1981 | 936 | 18500 | · | Final delivery | ||
2 | Faculty of Chemistry & Metallurgy | Iran University of Science & Technology | 1981 | 392 | 13700 | · | Final delivery | ||
3 | University of Kerman, Landscaping & Dormitory | University of Kerman | 1981 | 108 | · | Final delivery | |||
4 | Landscaping of the above faculties and around the university | Iran University of Science & Technology | 1983 | 62 | 20000 | · | · | · | Final delivery |
5 | Shipping line administrative building, Bandarabbas branch | The IRISL | 1983 | 334 | 6000 | · | · | · | Final delivery |
6 | Shipping line administrative building, head office | The IRISL | 1983 | 717 | 9000 | · | Completion of project | ||
7 | Design of clothing museum in Zahedan | Ministry of culture and art | 1983 | 50 | · | · | Completion of project | ||
8 | Interior design of cistern museum of Bandarabbas | Ministry of Culture & Art | 1983 | 100 | · | · | Completion of project | ||
9 | Design and implementation of the anthropological museum of Akbar house in Rasht, interior design and interior decoration design with furniture supply and accessories | Ministry of Culture & Art | 1984 | 1000 | · | · | · | Completion of project | |
10 | Services & educational building of Bank Maskan of Gorgan, landscaping | Bank Maskan | 1985 | 363 | 5500 building, 4000 landscaping | · | · | Completion of project | |
11 | Complementary work of military garrison 1 & 2 of Sirjan | Housing Organization (NEDAJA) | 1985 | 500 | 400000 | · | Completion of project | ||
12 | Environmental administrative & research complex of Esfahan | Department general of environment of Esfahan | 1985 | 180 | 2000 | · | · | · | Final delivery |
13 | Mirjaveh customs border complex, 72 administrative & residential sites | Department –general for housing and urban planning of Sistan- va-Balouchestan | 1986 | 1700 | 3000 | · | Final delivery | ||
14 | Central office of the university of sciences & defense industries –Shahinshahr | Defense industries organization | 1987 | 242 | · | · | · | Final delivery | |
15 | Comprehensive plan of university of sciences and defense industries – Shahinshahr | Defense industries organization | 1987 | 4580 | · | · | Comprehensive plan | ||
16 | Faculty of medical and paramedical sciences of Shahrekord | Ministry of Housing & Urban Planning | 1987 | 800 | 12000 | · | Stop | ||
17 | Faculty of medical & paramedical sciences of Yasouj | Ministry of Housing & Urban Planning | 1988 | 550 | 12000 | · | stop | ||
18 | Indoor swimming pool | The I.R.Iran Civil Aviation Organization | 1989 | 200 | 780 | · | Completion of project | ||
19 | Moghadam air base of Zahedan( | Aviation | 1989 | 4480 | 12500 buildings and 19500 landscapes | · | · | · | Final delivery |
20 | Environmental research & administrative complex of Kerman | Environment organization | 1989 | 500 | 1800 | · | · | Completion of project | |
21 | Environmental research & administrative complex of Yazd | Department –general for environmental protection of yazd | 1989 | 420 | 2000 | · | · | Completion of project | |
22 | Faculty of medical & paramedical sciences of Iranshahr | Ministry of housing & urban planning | 1989 | 1500 | 13200 | · | · | Completion of project | |
23 | Landscaping of garrison No. 3 of Sirjan | Ministry of defence and armed forces logistics | 1990 | 3570 | 400000 | · | Completion of project | ||
24 | Pottery brick factory of Tabriz | Bank Maskan | 1990 | 6000 | · | · | · | Final delivery | |
25 | Brick Factory of Firouzabad of Tehran | Bank Maskan | 1991 | 4500 | · | · | · | Final delivery | |
26 | University of strategic sciences | Chiefs of Staff Joint | 1991 | 6800 | 17000 | · | · | · | Completion of project |
27 | Indoor halls of pipe factories | Iran Spiral pipe factories | 1991 | 31800 | · | · | · | Final delivery | |
28 | Environmental research center of Semnan | Department-general for environmental protection of Semnan province | 1993 | 1250 | 3200 | · | · | Completion of project | |
29 | Detailed plan & preparation of Mahestan alley of Gheshm | Land & housing management of Gheshm free zone | 1996 | 50000 | 700000 | · | · | Completion of project | |
30 | Detailed plan and preparation of Sistan alley of Gheshm | Land & housing management of Gheshm free zone | 1996 | 35000 | 500000 | · | · | · | Completion of project |
31 | Alzahrah mosque of Kish Island | Kish development & civil company | 1996 | · | · | · | Completion of project | ||
32 | Detailed plan and preparation of the site adjacent to Naeim restaurant located on Gheshm | Land & housing management of Gheshm free zone | 1997 | 3000 | 60000 | · | · | Completion of project | |
33 | Detailed plan and preparation of Baharestan alley of Gheshm | Land & housing management of Gheshm free zone | 1997 | 45000 | 800000 | · | · | Completion of project | |
34 | Astara cultural and cinema complex | Department –general for Islamic Guidance of Guilan province | 1998 | 3600 | 1700 | · | Stop | ||
35 | Environmental research center of Shahrekord and visitor center for Tang Sayyad | Department –general for environmental protection of Chahar Mahal and Bakhtiari province | 1999 | 3570 | 2800 | · | · | · | Completion of project |
36 | Interior design of visitors gathering center of Golestan national park | Environmental protection department-general | 1999 | 300 | · | · | · | Completion of project | |
37 | Mosque and cultural complex of Bu-Ali Sina University | Bu-Ali-Sina University of Hamedan | 2001 | 5000 | · | · | · | Completion of project | |
38 | Iran Furniture Market | Mr. Ali Ansari and Partners | 2001 | 60000 | · | · | · | Final delivery | |
39 | Central building of the environmental research center of Qom province | Department-general for environmental protection of Qom province | 2002 | 3000 | 1200 | · | · | · | Completion of project |
40 | Indoor halls of hot rolling mills of Esfahan | Hot Rolling Mills of Esfahan | 2002 | 29000 | · | · | · | Completion of project | |
41 | Iran telecommunication development plan | Iran telecommunication researches center | 2002 | 220000 | 22000 | · | · | · | Completion of project |
42 | Sport complex design of Guilan province | Ports and shipping line department –general | 2002 | 6800 | · | · | · | Completion of project | |
43 | Mosque of Shiraz University | Sabzevar university | 2003 | · | · | · | Completion of project | ||
44 | Sport halls of Takestan, Boeinzahra, Mohammadieh | Department-general for physical education of Ghazvin province | 2003 | 18000 | 5400 | · | · | · | Completion of project |
45 | Environmental station of Brojen | Department –general for environmental protection of Chahar and Mahal and Bakhtiari province | 2003 | 2000 | 400 | · | · | Completion of project | |
46 | Mahmoudabad Resort | Iranian National Tanker Company | 2004 | 115000 | 10000 | · | · | · | Completion of project |
47 | Assaluyeh residential and administrative complex | Iranian National Tanker Company | 2004 | 120000 | 9000 + 10000 | · | · | · | Completion of project |
48 | Construction of assembly workshop and construction of gaseous liquids measurement systems | Asian instrumentation company | 2004 | 4500 | 850 buildings | · | · | Completion of project | |
49 | Bushehr inn | Iranian National Tanker Company | 2005 | 11000 | 1200 | · | · | Completion of project | |
50 | Establishment of industrial shed in Khark zone | Iranian National Tanker Company | 2004 | 22000 | 10000 | · | · | · | Completion of project |
51 | Amphitheater –building No. 2 | Iranian National Tanker Company | 2005 | 6000 | 600 | · | · | Completion of project | |
52 | Lavan inn | Iranian National Tanker Company | 2005 | 7000 | · | · | Completion of project | ||
53 | Renovation, repair and maintenance projects and maintenance of buildings, installations, and ports’ landscapes | Department –general for ports and marine of Guilan province | 2005 | 10000 | · | · | · | Completion of project | |
54 | Landscaping project around technical faculty and mosque and designing the faculty of physical education | Islamic Azad University of Karaj | 2006 | 28000 | 16000 | · | · | Completion of project | |
55 | 15-class technical school of Shahid Abbaspour of Semnan | School renovation and equipment organization | 2007 | 40000 | 5600 | · | · | Completion of project | |
56 | Renovation, repair and maintenance projects and maintenance of buildings, installations, and ports’ landscapes | Department –general for ports and marine of Guilan province | 2007 | 10000 | · | · | · | Final delivery | |
57 | Khorramdareh public library | Housing and urban planning department-general for Zanjan province | 2008 | 7500 | 900 | · | · | · | Final delivery |
58 | Mosque of Malayer university | Malayer University | 2008 | · | · | · | Final delivery | ||
59 | Parand residential complex | Karaj martyr and veterans’ affairs foundation | 2009 | 200000 | 56000 | · | Stop | ||
60 | Renovation, repair and maintenance projects for the buildings | Department –general for ports and marine of Guilan province | 2009 | 12000 | · | · | · | Final delivery | |
61 | Renovation, repair and maintenance projects for the buildings | Department –general for ports Bushehr province | 2010 | 20000 | · | · | · | Final delivery | |
62 | Renovation, repair and maintenance projects for the buildings | Department –general for ports and marine of Guilan province | 2011 | 15000 | · | · | · | Completion of project, final delivery | |
63 | Sarv residential welfare complex | Iranian National Tanker Company | 2010 | 12000 | 2500 | · | · | · | Final delivery |
64 | 2000-seat multi-purpose gym | Chahbahar free zone | 2010 | 40000 | 4000 | · | · | Completion of project | |
65 | Designing Roodhen tourism & handicraft special zone | Jewelry and gold production and distribution cooperative | 2011 | 200000 | · | · | · | Completion of project | |
66 | Providing design services for the electricity substation of the Central Bank Maskan | Navaco information and technology company | 2013 | 510 | · | · | · | Completion of project | |
67 | Providing PM consulting services for the buildings and installation | Department –general for ports and marine of Guilan province | 2013 | 880 | · | · | · | Final delivery | |
68 | Providing design services for phase 1 & 2 of 15 Khordad branch of Samen Al Aemeh bank of Gorgan | Samen Al Aemeh credit and cooperative development bank | 2013 | 500 | · | · | Completion of project | ||
69 | Providing the consulting services for preventive maintenance (PM) &repair and preparing tender documents for Anzali port buildings | Department –general for ports and marine of Guilan province | 2014 | 1120 | · | · | · | Final deliveyr | |
70 | Performing triple consulting services and studies of the sport complex, fire department of Anzali port | Department –general for ports and marine of Guilan province | 2015 | 8030 | · | · | · | Final delivery | |
71 | Providing services of the 3rd stage of the overhaul project leading to PM of administrative building | Department –general for ports and marine of Sistan va Baluchistan province | 2015 | 9380 | · | · | · | Temporary delivery | |
72 | Providing 3rd stage of the overhaul project leading to PM of 20 units of organizational green houses located at Bandar Chabahar alley | Department –general for ports and marine of Sistan va Baluchistan province | 2017 | 6060 | · | · | · | Temporary delivery | |
73 | Providing design services for the 2nd stage: preparing tender documents and consulting services of overhaul projects and repairing and maintaining buildings, installation and case services of Chabahar port | Department –general for ports and marine of Sistan va Baluchistan province | 2017 | 2000 | · | · | Completion of project | ||
74 | 3rd stage services of repair and maintenance of periodic and emergency services (PM & EM) of building and mechanical installation of port’s buildings and landscapes | Department –general for ports and marine of Sistan va Baluchistan province | 2018 | 20000 | · | · | · | Temporary delivery | |
75 | 3rd stage services of overhaul project leading to PM of health building of koye Chabahar housing | Department –general for ports and marine of Sistan va Baluchistan province | 2018 | 2670 | · | · | · | Temporary delivery | |
76 | 1st & 2nd services of overhaul project leading to PM of buildings located at Khark Island | Department –general for ports and marine of Bushehr province | 2018 | 2456 | · | · | Completion of project | ||
77 | 3rd stage services of overhaul project leading to PM of buildings located at Khark Island | Department –general for ports and marine of Bushehr province | 2020 | 16100 | · | ||||
78 | 1 st & 2nd stage services of mechanical and electrical installation of Farmaniyeh building | Pishgam Azarestan Co. | 2023 | 6100 | 15250 | · | · | in process | |